Latest News
Offshore Wind Power Development In Taichung Port
2018-01-03
臺中港離岸風電發展規劃
Offshore Wind Power Development In Taichung Port
為配合為行政院推動離岸風電於民國119年達3GW裝置容量之目標,臺中港離岸風電產業專區規劃如下:(如下圖表)
- 碼頭及預組裝區:第1組裝區#5A、#5B碼頭2座暨後線相關土地約12.8公頃;第2組裝預備區#38、#39號碼頭暨後線相關土地約24.67公頃。
- 國產化製造組裝區:#106號碼頭暨工業專業區土地約107.38公頃。
The goal of offshore wind power capacity by 2030 will be 3GW.
In Taichung port, the scope of offshore wind power development is:
1、There are two sections concerning turbine assembly terminal. One is at the areas of #5A, #5B wharf and the rear lands of them(12.8ha). The other is # 38, #39 wharf and the rear lands of them(24.67ha).
2、Localized turbine parts manufacturing: #106 wharf and the rear lands of them (5.1ha)and Industrial Zone (Ⅱ), total area is 107.38 ha.
臺中港離岸風電產業專區
Offshore Wind Power Development In Taichung Port
|

|
預估時程表
Potential Industry
|
項目
Item
|
概述
Description
|
興建期程
Construction schedule (estimated)
|
#5A、#5B碼頭
Construction of Wharf #5A and #5B |
- 碼頭共400公尺 (400m in length)
- 水深11公尺(Depth of water: -11m)
- 碼頭承載力50噸/m2(Heavy-bearing-capacity:50ton/m2)
|
- #5A碼頭於2018年完工(Wharf #5A: to be completed by Y2018)
- #5B碼頭於2019年完工。(Wharf #5B: to be completed by Y2019)
- 後線12.8公頃土地。(Storage area:12.8ha)
|
#38、#39碼頭
Construction of Wharf #38 and #39 |
- #38碼頭長度330m(Wharf #38:330m in length)
- #39碼頭長度330m(Wharf #39:357m in length)
- 水深16公尺( Depth of water: -16m)
|
- 碼頭視業者需求興建。(Construction of Wharf Depend on following design)
#38碼頭土地面積330m x 450m。
#39碼頭土地面積:357m x 188m
|
#106碼頭
Construction of Wharf #106
|
- 重件碼頭長度100公尺(Heavy-bearing-capacity part: 100m)
- 一般碼頭230公尺(General-bearing-capacity part: 230m)
- 水深16公尺(Depth of water: -16m)
|
- 2018年完成重件段100公尺。Heavy-bearing-capacity part (100m): to be completed by Y2018
- 2019年完成一般段230公尺。General-bearing-capacity part (230m): to be completed by Y2020
|
工業專業區(Ⅱ)專業道路
Construction of public road and facilities on Industrial Zone (Ⅱ) |
- 新建南北約2,600m道路、東西向700m道路、寬30m
- South-north road: 2,600m in length, 30m in width
- East-west road: 700m in length, 30m in width
|
- 2018年完成新建南北向道路。South-north road: to be completed by Y2018
- 2019年完成新建東西向道路 East-west road: to be completed by Y2019
|
|
最後更新日期:106-11-22 |